PERT chart vs Gantt chart: A first glance comparison

PERT Chart vs Gantt Chart

Two of the most popular project management charts are the PERT chart and the Gantt chart. Both charts are designed to help project managers plan, execute, and monitor project progress, but they serve different purposes and benefits.

Understanding the differences between PERT and Gantt charts can help you decide which is best suited for your project needs and when you should use them.

In this article, we will understand what is Gantt and PERT Charts, their key differences, and which one you should use.

What is a PERT Chart?

A PERT chart is a project management tool used to schedule, organize, and coordinate tasks within a project. It is a graphical representation of the project schedule and shows the relationship between the various tasks and their durations. It is used to estimate the time required to perform a project or a task.

In this method, each task related to the project is assigned a critical path. The critical path represents all those activities that must be completed before other activities can begin (or continue), as depicted by arrows in a diagram. The sum of all activity times must equal the “total project duration” (time taken for completion).

PERT (Program Evaluation Review Technique) Charts are used primarily when dealing with uncertainty or risk mitigation because they allow you to plan even if things change during execution! Additionally, they can help you keep track of performance so that you know if your team has been successful at meeting deadlines throughout the execution period.

What is a Gantt Chart?

A Gantt chart is a type of bar chart that represents a project schedule. Gantt charts are used to track the project’s progress over time. It provides a simple visual overview of the project timeline and helps managers allocate resources and track task completion effectively.

Gantt charts can be created using Microsoft Project software or any other spreadsheet program such as Excel. The Gantt chart consists of two main sections, namely:

  • A timeline that shows how long each task will take and when it will start/end.
  • A table with rows for each resource name and column headers that include information about each task, such as its duration and start date/time/etc.

Difference between the PERT chart and the Gantt chart

The main difference between a PERT Chart and a Gantt Chart is that a PERT Chart focuses on identifying task dependencies and estimating the time needed for each task using a network diagram, making it ideal for planning and analyzing the critical path of a project. Whereas, a Gantt Chart provides a visual timeline of tasks, showing their start and end dates, durations, and progress, which is useful for tracking the schedule and managing resources throughout the project.

Let’s know in detail:

1. Gantt Chart is based on project management theory.

Gantt-chart-Proofhub

Gantt Charts are based on Project Management Theory. Developed in 1910 by Henry Gantt, a Gantt chart displays each task required by a given project linearly. 

Using this timeline view, you can easily determine the expected duration of each task (as well as the overall project). In addition to visualizing the order of specific tasks, Gantt charts also allow you to identify the individuals and teams responsible for each one.

Gantt Chart is used to display the project schedule, plan or schedule tasks, and manage project resources. It is helpful in identifying the critical path of a project. 

2. PERT Charts use the critical path method

The US Navy first proposed a PERT chart in 1957, but it wasn’t widely used until about 30 years later when there was a surge of interest in project management practices.

The PERT Chart uses the critical path method to determine the longest path through a project. The critical path method is used to determine the earliest completion date, latest completion date, and earliest start date.

The critical path method is a network analysis technique used in project management to identify the minimum time required to complete an entire project. This technique seeks out activities that are directly related to each other and calculates their duration (start-to-finish) based on dependencies between them. Suppose an activity does not have any dependency. In that case, it is called independent activity or non-critical activity because they don’t add up to any delay in finishing off other tasks or projects at hand. However, if there exists some dependency then those tasks will be considered as “critical” activities or simply “critical paths”.

3. PERT Charts can be used to plan tasks

PERT Charts are used to plan a project. They are more suitable for projects with multiple tasks, milestones, or deliverables. The PERT Chart should be created using the following steps:

  • Select activities required for your project
  • Determine their sequence or order of completion
  • Estimate each activity’s duration (how long will it take you to complete it?)
  • Add an optimistic estimate (best-case scenario), most likely estimate (a most likely scenario), and pessimistic estimate (worst-case scenario). These three estimates are known as E(expected), M(medium), and U(under-run).

If you add up all the expected durations and divide that sum by 6, then your calculations will always fall within 80% – 120%. If your calculation falls outside this range, then something could be wrong with your estimates!

4. Gantt Charts show the project schedule.

In a Gantt chart, the tasks are listed in chronological order, along with their durations and dates. The horizontal line is known as the “bar,” while vertical lines represent each task or subtask. The only thing that can be seen in a Gantt chart is how your project will be scheduled throughout its duration, but there is no information about how well it’s being executed on a day-to-day basis.

When and which chart should you use?

Gantt Charts and PERT Charts are two of the most widely used project management tools. Both are great for planning your project, but there are some key differences: Gantt charts use a theoretical approach and show only the schedule, while PERT charts use the critical path method to calculate how long each task will take.

 PERT ChartGantt Chart
Project ScopeIt is recommended to use PERT charts during the planning phase of a project, as they allow users to mapGantt charts are more helpful once a project is underway, as they can be adjusted if the scope changes.
TimelineIt is based on a particular formula that PERT charts calculateBy using a Gantt chart, activities are planned and scheduled, allowing notifications when a timeline has been missed.
FlexibilityPERT charts are challenging to change mid-project, making them a less flexible option.Projects and plans can be changed more easily with Gantt charts.
Task AssignmentUsing a PERT chart allows team members to quickly see which tasks are dependent on each other and who is responsible for what.Gantt charts tend to be very large and complex, often requiring team members to scroll through many pages in order to see the big picture.

It is important to understand the difference between these two types of project management charts to know which chart to use and when it is important to understand them.

Why should you use the Gantt chart view?

Gantt charts are great for project planning. They help you to stay on track and plan better by giving you an idea of what needs to be done, who will do it, when it needs to be done, and how much it will cost.

Gantt charts are great for project presentations. It helps in presenting the status of a project by providing a visual representation of the schedule in the form of bars or rectangles with time codes on them so that everyone knows exactly where he/she stands in terms of completion with respect to others working on similar tasks; this makes it easier for teams to work together as one unit rather than as individuals who may not understand each other’s roles perfectly well even though they might be working on similar tasks themselves.

Gantt charts are great for project management because managers can use the Gantt chart tool effectively when communicating their goals and expectations about projects being completed within certain time frames; by using Gantts, managers can ensure that employees get clear direction regarding objectives without having any miscommunication issues arise later down the line during implementation stages (such as workload distribution). This helps us all know exactly what needs doing now while also allowing us to identify potential risks early enough so they don’t become big problems later down the road.”

How to create a Gantt Chart using the ProofHub tool

Creating a Gantt Chart in ProofHub is easy.

  • Go to your project dashboard and click on the ‘Gantt Chart’ button (you’ll see this at the top of your page).
  • Select the project type: Milestone or Task.
  • Select a duration for your project—that’s how long it should take to complete, in days or hours.
  • Give your project a name and select its start date, end date, start time, and end time.

Easily plan and manage projects to stay on top of your deadlines and projects using Gantt Charts in Proofhub. Get started for free!

Conclusion

Ultimately, both a PERT and Gantt chart are only as useful as the skill of the person using them. If you’re still not sure which type of chart to use, or you’ve settled on one but aren’t sure how it works, make sure you talk with someone who has experience with the tool. They can teach you the ins and outs of the process, allowing you to put them to work better in your projects in the future.

Try ProofHub, our powerful project management and team collaboration software, for free!

 No per user fee.   No credit card required.   Cancel anytime.

Contents